Which construction approach allows for starting the process before contract completion?

Prepare for the Arkansas NASCLA Contractors Exam. Use flashcards and multiple choice questions, each with hints and explanations, to master your exam material.

Fast-track construction is an approach that allows for portions of the construction project to commence before the entire contract has been finalized. This method is particularly effective for large or complex projects where time is a critical factor. By overlapping design and construction phases, fast-track construction helps to expedite the project timeline, allowing early site work or the construction of specific phases to begin while final designs or remaining contracts are still being negotiated or finalized.

This can lead to significant time savings, as certain elements can be completed and utilized while other parts of the project are still under development. The process requires careful management and coordination to ensure that all components align correctly as the project progresses, which is where the expertise of the project team becomes essential.

In contrast, traditional construction methods typically follow a sequential approach requiring the complete design and bid process to be finalized before any construction activities can begin, leading to longer project timelines. Similarly, design-bid-build and negotiated construction methods do not inherently allow for such overlapping activity, as they rely on a complete contract and finalized designs before any construction work starts.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy